Timeline
How we are going to get there

Mid 2011

The gallery opens to the public


Late 2010

Building construction completed and building handed back to Auckland City Council


March 2010

Roof completed


February 2010

Third floor completed


December 2009

Second floor completed


November 2009

First floor completed


August 2009

Ground floor level completed


May 2009

Basement completed


November 2008

Wellesley & Kitchener wings and East Gallery revealed after demolition


September 2008

Construction begins


August 2008

Environmental court grants resource consents


March 2008

Central Governement contributes $30 million


Early 2008

Detailed design concludes
Construction tender let
Closure of the main building
Construction commences
Exhibitions and events will continue to be held at the Auckland Art Gallery, New Gallery


Early 2006

Lodge for resource consent approvals as required under RMA


July 2005

Initial design concepts launched


July 2004

Fjmt + Archimedia appointed as architects


 

 

 